Union Bleachery Mill Village Project
MetroConnects is excited to begin its critical infrastructure replacement project in the Union Bleachery community. This project is supported by a $4M State and Tribal Assistance Grant, approved by the Senate Appropriations Committee in for FY2023. Metro is grateful for Sen. Lindsay Graham’s commitment to funding wastewater improvement projects that are transformative for residents of Greenville County.
During the first phase of this project, more than 4,953 linear feet of gravity sewer will be replaced and relocated, as well as 27 new manholes installed. During the process, Metro will abandon 8,615 linear feet of VCP or clay pipes and 120 manholes that have been in the ground since about 1906 when the first homes were constructed in the mill village. Metro also will rehabilitate 224 linear feet of a 15-inch sewer main with Cured-In-Place (CIPP) lining to prevent open cut construction across a waterway.
The project is expected to begin in late May.
Additional Information:
Crews will work diligently Monday through Friday between the hours of 8 a.m. and 5 p.m., excluding holidays. Every effort will be made to minimize disruption to the homeowners and to complete the work quickly. The contractor will notify residents in-person and through door hangers of any construction that may impact their homes.
Signage also will be placed in construction areas and will feature QR codes directing customers to the CDM Smith and MetroConnects websites for additional information.
Please note that portions of the street may be closed during the day. Roadways will be plated in the evenings to allow residents easier passage in the evenings.